Mathematics · PERT and CPM
The optimistic time, most likely time, and pessimistic time estimates for a project activity are 6 days, 7 days, and 8 days respectively. What is the expected completion time of this activity?
- 17 days✓
- 26 days
- 39 days
- 412 days
Correct answer
7 days