The optimistic, most likely, and pessimistic time estimates for an activity are 6, 16, and 22 days respectively. What is the probabilistic expected time (te) estimate?
- 129.33 days
- 214.66 days
- 330.66 days
- 415.33 days✓
Correct answer
15.33 days