The normal duration and normal cost of an activity are 24 days and Rs. 50,000 respectively. The activity can be crashed to a minimum duration of 22 days. The indirect cost is Rs. 1,000 per day and the cost slope of the activity is Rs. 1,500 per day. What will be the total network cost of the project activity after crashing it completely?
- 1Rs. 45,500
- 2Rs. 51,000✓
- 3Rs. 54,500
- 4Rs. 47,500
Correct answer
Rs. 51,000