Computer · Hydrology and Water Resources Engineering
The mass curve method for the determination of the storage capacity of a reservoir utilizes which of the following data parameters?
- 1Census data and cash flow
- 2Cash flow data and water flow data
- 3Water inflow data and water demand data✓
- 4Water demand data and water wastage data
Correct answer
Water inflow data and water demand data