The low power factor adjustment of a single-phase energy meter is carried out by connecting the pressure coil across ______, and supplying the current coil with ______ at a power factor of ______.
- 1rated voltage; rated full load current; 0.707 lagging
- 2rated voltage; rated full load current; 0.5 leading
- 3rated voltage; rated full load current; 0.5 lagging✓
- 4half of rated voltage; half of rated full load current; 0.5 leading
Correct answer
rated voltage; rated full load current; 0.5 lagging
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Electrical Measurements?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Electrical Measurements