Computer · Construction Management
The immediate predecessor activities of activity D are A, B, and C. Given that the earliest finish times of activities A, B, and C are 10, 12, and 16 days respectively, what will be the earliest start time of activity D?
- 116 days✓
- 238 days
- 312 days
- 410 days
Correct answer
16 days