The fuel cost functions in rupees/hour for two 600 MW thermal power plants are given by: Plant 1: C1 = 350 + 6P1 + 0.004(P1)2 Plant 2: C2 = 450 + 5.3P2 + 0.003(P2)2 where P1 and P2 are the power generated by Plant 1 and Plant 2 in MW respectively. If the two plants together meet a total power demand of 550 MW optimally under incremental cost scheduling, what is the optimal generation (in MW) of Plant 1 and Plant 2 respectively?
- 1200 and 350
- 2325 and 225
- 3350 and 200
- 4250 and 300✓
Correct answer
250 and 300
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Economic Operation of Power Systems?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Economic Operation of Power Systems