Computer · Construction Management
The 'Force-Majeure' clause in a contract document generally refers to which of the following unforeseen circumstances? (1) Agitations and strikes (2) Epidemics of large proportion
- 1None of the above
- 2Both (1) and (2)✓
- 3Only (2)
- 4Only (1)
Correct answer
Both (1) and (2)