General Studies · Industrial Engineering and Project Management
The following statements represent the formulation of project activities using the Critical Path Method (CPM). Among them, one criterion is INCORRECT. Identify the incorrect statement.
- 1The technique involves the completion of projects having activities of a repetitive nature.
- 2Emphasis is given on the starting and completion of an event rather than on the activities required to be performed to reach a particular event.✓
- 3The technique was developed with regard to the construction and maintenance of projects in which the duration of each activity is known with certainty.
- 4It is suitable for establishing a trade-off for optimum balancing between schedule time and cost of the project.
Correct answer
Emphasis is given on the starting and completion of an event rather than on the activities required to be performed to reach a particular event.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering and Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering and Project Management