Economics · Budgeting
The following statements have been made about flexed budgets: 1. The flexed budget is prepared at the expected level of activity. 2. The flexed budget is used to identify variances caused by a different level of activity to what was budgeted. 3. The flexed budget uses the original budget assumptions in relation to selling price and cost per unit. Which of the above statements is/are correct?
- 12 only
- 22 and 3✓
- 33 only
- 41 and 2
Correct answer
2 and 3
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Budgeting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Budgeting