Mathematics · Inventory Management
The following information relates to Blanc Co's inventory metrics: - Annual demand: 400,000 units - Order quantity: 70,000 units - Reorder level: 30,000 units - Lead time: 3 weeks Assuming there are exactly 50 weeks in a working year, what is the buffer (safety) level of inventory?
- 16,000 units✓
- 240,000 units
- 330,000 units
- 424,000 units
Correct answer
6,000 units