Physical Education · Sports Management
The D.I.M. (Develop, Implement, Manage) process is a widely used method to establish a:
- 1Budget Management Programme
- 2Risk Management Programme✓
- 3Personnel Management Programme
- 4Supervising Management Programme
Correct answer
Risk Management Programme