The Critical Path Method (CPM) was developed independently as a network technique. It differs from PERT primarily because CPM is a:
- 1Probabilistic approach based on Gantt charts
- 2Event-oriented probabilistic model
- 3Sub-element directly evaluated from a standard bar chart
- 4Deterministic approach focused on activity duration and cost trade-offs✓
Correct answer
Deterministic approach focused on activity duration and cost trade-offs
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management