Mathematics · Project Management - CPM
The Critical Path Method (CPM) is suitable for which type of projects?
- 1Research projects with uncertain activity durations
- 2Both small and large projects with deterministic activity times✓
- 3Large projects only
- 4Small projects only
Correct answer
Both small and large projects with deterministic activity times