Computer · Construction Management
The crash project duration in network analysis is accurately obtained by summing the:
- 1Normal durations for all the activities in the network
- 2Crash durations for all the activities in the network
- 3Crash durations for all activities along the critical path that was originally determined using normal durations
- 4Crash durations for all the activities along the new critical path obtained by fully considering the crash durations of the activities✓
Correct answer
Crash durations for all the activities along the new critical path obtained by fully considering the crash durations of the activities
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management