Computer · Estimation and Costing
The contract in which the contractor needs to complete the work within a fixed sum and fixed time, irrespective of the quantities of different items, is:
- 1Fixed contract
- 2Lump sum contract✓
- 3Item rate contract
- 4Schedule contract
Correct answer
Lump sum contract