The construction of a PERT network diagram essentially revolves around four key interdependent terms. These terms are events, activities, ________, and ________.
- 1Slack time; critical path✓
- 2Crucial path; earliest date
- 3Crucial path; slack time
- 4Critical path; estimated time
Correct answer
Slack time; critical path