Computer · Concrete Technology
The construction joints in cement concrete:
- 1Should be located where bending moment is large
- 2Should be located where shear force is large
- 3Should not be provided at the corners✓
- 4Should be spaced at a distance of 3 m apart in case of huge structures
Correct answer
Should not be provided at the corners