Computer · Highway Engineering
The base course of a Water Bound Macadam (WBM) road consists of:
- 1120 to 180 mm stone placed on their ends upwards + 50 mm stone Macadam + water + 2 layers of metal each 150 mm thick + Rolled + Screenings applied.✓
- 2120 to 180 mm stone placed on their ends upwards + 50 mm stone Macadam + water + 2 layers of metal each 150 mm thick.
- 3120 to 180 mm stone placed on their ends upwards + 50 mm stone Macadam + water.
- 4120 to 180 mm stone placed on their ends upwards.
Correct answer
120 to 180 mm stone placed on their ends upwards + 50 mm stone Macadam + water + 2 layers of metal each 150 mm thick + Rolled + Screenings applied.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Highway Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Highway Engineering