Mathematics · Estimation and Costing
The approximate quantity of brickwork in lime or cement mortar in foundation and plinth done by an average artisan per day is:
- 150 cu ft (1.42 m 3 )
- 235 cu ft (1.00 m 3 )
- 320 cu ft (0.56 m 3 )
- 445 cu ft (1.25 m 3 )✓
Correct answer
45 cu ft (1.25 m 3 )