Computer · Construction Management
The amount of time by which the completion of an activity can be delayed without affecting the earliest start time of any succeeding activity is known as:
- 1earliest completion time
- 2total float
- 3free float✓
- 4independent float
Correct answer
free float
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management