Mathematics · Time and Work
T can complete a work in 20 days and U can complete the same work in 10 days. If both of them work together, then in 4 days what percent of the total work will be completed?
- 180 percent
- 275 percent
- 365 percent
- 460 percent✓
Correct answer
60 percent
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work