Mathematics · Time and Work
Suresh can do a piece of work in 9 days and Nimesh can do the same work in 18 days. They work together for 4 days, after which Suresh leaves. How many days will Nimesh alone take to complete the remaining work?
- 14 days
- 26 days✓
- 37 days
- 45 days
Correct answer
6 days