Sloan Co absorbs overheads on machine hours. In a period, actual machine hours were 22,435, actual overheads were $496,500 and there was over absorption of $64,375. What was the budgeted overhead absorption rate per machine hour (to the nearest $)?
- 1$29
- 2$27
- 3$26
- 4$25✓
Correct answer
$25