Mathematics · Time and Work
Six men can complete a work in 14 days. They started the work and after 5 days, three men left. In how many total days will the work be completed from the start?
- 115 days
- 223 days✓
- 320 days
- 418 days
Correct answer
23 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work