Sequence correctly the following steps in PERT/CPM network analysis: (A) Identify the critical path (B) Draw the network diagram (C) Establish dependencies across activities (D) Estimate the completion time of an activity (E) Define the activities in the network Choose the correct option from the choices given below:
- 1(A), (B), (D), (E), (C)
- 2(C), (B), (E), (A), (D)
- 3(E), (C), (B), (D), (A)✓
- 4(B), (C), (D), (E), (A)
Correct answer
(E), (C), (B), (D), (A)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Business Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Production and Operations Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Business Studies · Production and Operations Management