Select the correct statement regarding Cross Drainage Works:
- 1The canal always carries a higher discharge than the natural drain in all types of cross drainage works.
- 2The position of the canal and drain relative to each other can be chosen arbitrarily irrespective of their bed levels.
- 3The drain flows below the canal in an aqueduct and siphon aqueduct, and the drain flows above the canal in a super passage and canal siphon.✓
- 4The canal flows below the drain in an aqueduct, and above the drain in a super passage.
Correct answer
The drain flows below the canal in an aqueduct and siphon aqueduct, and the drain flows above the canal in a super passage and canal siphon.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Irrigation Engineering - Cross Drainage Works?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Irrigation Engineering - Cross Drainage Works