Select the correct option regarding the two statements: Assertion (A): Delays in construction projects can significantly increase the total project cost. Reason (R): Project delays result in higher indirect costs such as site overheads and equipment rentals.
- 1Both A and R are true, and R is the correct explanation of A.✓
- 2A is true, but R is false.
- 3Both A and R are true, but R is not the correct explanation of A.
- 4A is false, but R is true.
Correct answer
Both A and R are true, and R is the correct explanation of A.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management