Select the correct chronological sequence of the stages involved in a conventional surface water treatment plant.
- 1Filtration, aeration, screening, disinfection, sedimentation
- 2Screening, aeration, sedimentation, filtration, disinfection✓
- 3Aeration, screening, filtration, sedimentation, disinfection
- 4Screening, filtration, aeration, sedimentation, disinfection
Correct answer
Screening, aeration, sedimentation, filtration, disinfection
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Environment & Ecology?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Environmental Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Environment & Ecology · Environmental Engineering