Select the correct bottom-to-top construction sequence for the different layers of a standard flexible pavement: i. Base course construction ii. Subbase course construction iii. Surface course and seal coat application iv. Natural subgrade and compacted subgrade preparation v. Prime coat, binder course and tack coat application
- 1(iv), (v), (i), (ii), (iii)
- 2(iv), (ii), (i), (v), (iii)✓
- 3(i), (iii), (v), (ii), (iv)
- 4(i), (ii), (iii), (iv), (v)
Correct answer
(iv), (ii), (i), (v), (iii)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Transportation Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Transportation Engineering