Seema can finish a work in 7 days, while Kartik can finish the same work in 12 days. If they work together, how many days will they take to complete the work? (Round to two decimal places)
- 14.42 days✓
- 24.89 days
- 35.12 days
- 43.42 days
Correct answer
4.42 days