Sanju can do a piece of work in 17 days and Rohan can do the same work in 68 days. Find the time required to complete the work if they work on alternate days and Sanju starts the work on the first day.
- 11094 days
- 21074 days✓
- 3414 days
- 41054 days
Correct answer
1074 days