Samir takes 6 days and Tanvir takes 8 days to complete a piece of work individually. They undertook the work together for ₹2,400. With the help of Amir, they completed the work in 3 days. What amount should be paid to Amir?
- 1₹300✓
- 2₹800
- 3₹700
- 4₹500
Correct answer
₹300