Robert, Chris, and Jeremy can finish a certain piece of work in 16, 48, and 32 days, respectively. All three of them started the work together. Robert left the work after 2 days and Chris left just 4 days before the work was completed. Find the total number of days taken for the work to be completed.
- 116.2
- 218.4✓
- 324.3
- 417.7
Correct answer
18.4