Removing the old metal on a road surface, reconsolidating it by adding more metal, and repainting the top surface of the road is reflected in which type of estimate?
- 1Revised estimate
- 2Special repairs estimate✓
- 3Annual repairs estimate
- 4Supplementary estimate
Correct answer
Special repairs estimate