General Studies · Operations Research
Read the following statements regarding PERT and CPM: (a) PERT is probabilistic in nature and CPM is deterministic in nature. (b) PERT is suitable for new projects, whereas CPM is of great value for repetitive projects. (c) PERT focuses primarily on the time element, while CPM puts strong emphasis on cost optimization alongside time. (d) PERT is activity-oriented and CPM is event-oriented. Which one of the following options contains all the correct statements?
- 1(a) and (d)
- 2(a), (c) and (d)
- 3(a), (b), (c) and (d)
- 4(a), (b) and (c)✓
Correct answer
(a), (b) and (c)
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Operations Research