Computer · Estimating and Costing
Rate analysis in civil engineering projects involves the detailed calculation of:
- 1Only the quantities of raw materials required
- 2Only the cost of specialized and manual labour
- 3Materials, labour, contractor profit, and overheads✓
- 4Only the depreciation of machinery and equipment
Correct answer
Materials, labour, contractor profit, and overheads