Mathematics · Time and Work
Ramesh and Suresh can complete a piece of work in 10 days and 12 days, respectively. If they work on alternate days, starting with Ramesh, in how many days will the entire work be finished?
- 11211 days
- 2101011 days
- 31256 days
- 41056 days✓
Correct answer
1056 days