Mathematics · Time and Work
Raman can complete a piece of work alone in 27 days, while Raman and Suraj together can complete the same work in 18 days. If they receive a total payment of Rs. 12,000 for completing the work together, what is Suraj's share?
- 1Rs. 4,000✓
- 2Rs. 2,000
- 3Rs. 6,000
- 4Rs. 5,000
Correct answer
Rs. 4,000