Ram can finish a piece of work in 6 days working 10 hours each day. After working for 3 days (10 hours a day), he starts working 6 hours a day to finish the remaining portion of the job. What is the total number of days Ram would require to finish the entire job?
- 110 days
- 28 days✓
- 312 days
- 415 days
Correct answer
8 days