Rajender engages Sunil and Vijay to do some construction work in his office. Sunil is highly skilled and is 312 times as good a workman as Vijay. Therefore, he is able to finish his work in 45 days less than Vijay. In how many days, working together, can they finish the work?
- 114 days✓
- 218 days
- 322 days
- 426 days
Correct answer
14 days