Raj takes 45 days more than Simran to complete a piece of work, while Simran's efficiency is 53 of Raj's efficiency. Raj, Simran, and Priya start working together and complete the work in 20 days. In how many days can Priya alone complete the work?
- 152 813 days
- 246 1217 days
- 342 611 days
- 438 271 days✓
Correct answer
38 271 days