Mathematics · Time and Work
Rahul can complete a piece of work in 20 days while Rohan can do the same work in 30 days. Both started working together and worked at full efficiency for 6 days, and at half their efficiency for the next 6 days. In how many days will the remaining work be completed if both work at full efficiency from then on?
- 17
- 25
- 310
- 43✓
Correct answer
3