Project scheduling involves various structured processes to ensure timely completion. Which of the following is NOT a primary step in project scheduling?
- 1Calculating the start and finish times for activities
- 2Deciding the logical sequence of activities
- 3Giving subjective feedback on performance✓
- 4Assigning resources to distinct activities
Correct answer
Giving subjective feedback on performance