Industrial Engineering · Network Analysis
PERT के विपरीत, क्रांतिक पथ पद्धति (Critical Path Method - CPM) के लिए आवश्यक है:
- 1चार समय का अनुमान (four time estimates)
- 2त्रिसमय अनुमान (three time estimates)
- 3दोहरे समय का अनुमान (two time estimates)
- 4एकल समय अनुमान (single time estimate)✓
सही उत्तर देखें
एकल समय अनुमान (single time estimate)