Computer · Construction Management
PERT (Program Evaluation and Review Technique) analysis is based on which of the following time estimates? (i) Optimistic time (ii) Most likely time (iii) Pessimistic time
- 1only (i)
- 2only (ii)
- 3only (i) and (ii)
- 4(i), (ii) and (iii)✓
Correct answer
(i), (ii) and (iii)