Perform CPM (Critical Path Method) analysis for the given project data and identify the Critical Path: Activity A (Predecessor: none, Duration: 3 weeks) Activity B (Predecessor: A, Duration: 5 weeks) Activity C (Predecessor: A, Duration: 4 weeks) Activity D (Predecessor: B, Duration: 7 weeks) Activity E (Predecessor: C, Duration: 6 weeks) Activity F (Predecessor: D, E, Duration: 2 weeks)
- 1A → C → D → F
- 2A → B → E → F
- 3A → B → D → F✓
- 4A → C → E → F
Correct answer
A → B → D → F
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management