Mathematics · Time and Work
Pawan, Manoj, and Rohan can complete a work in 6, 8, and 12 days respectively. Pawan works every day and is helped alternately by Manoj one day and Rohan the next day. In how many days will the work be completed?
- 1223 days
- 2313 days
- 3323 days✓
- 4113 days
Correct answer
323 days