Mathematics · Cost Accounting
Park Co is developing a number of new products. New legislation means that one of these products will not be viable unless additional expenditure, estimated at $2 million, is undertaken. This amount excludes $100,000 which is the estimate of the contribution potentially lost through the delay to another project due to the transfer of resources. To date $4.7 million has been spent on the project. It is estimated that before the change in legislation, $3 million was required to bring the product to the launch stage. What is the sunk cost of the project?
- 1$4,700,000✓
- 2$7,700,000
- 3$2,100,000
- 4$100,000
Correct answer
$4,700,000
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length Mathematics mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Cost Accounting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Cost Accounting