P, Q, and R working alone can complete a work in 24, 30, and 40 days respectively. All three started the work together, but after 8 days P left. Q left the work 6 days before its completion, and R completed the remaining work alone. In how many days was the total work completed?
- 11527
- 21097
- 31047✓
- 4977
Correct answer
1047